South Canal Drop 4 Hydro

  • Size: 4.8 MW
  • Date Built: 2015
  • Nearest Town: Montrose, Colorado
  • Head: 74 ft
  • Flow: 840 CFS
  • Unit details: Vertical double regulated Kaplan; synchronous generator
  • Penstock diameter: 120″
  • Penstock length: 1,400′
  • Additional details: 75′ deep power house excavation (50,000 cubic yards). Automatic trip gates installed. Irrigation water.

Back to Projects